Road improvements are scheduled in the Vista Run neighborhood (Phases 3 & 4) beginning Friday, July 10, weather permitting. Work includes milling, patching, and final paving.
Tentative Schedule
Prep Work
- Friday, July 10: Mill & Clean – Phase 3
- Saturday, July 11: Mill & Clean – Phase 4
- Saturday, July 11: Patching – Phases 3 & 4
Paving
- Monday, July 13: Phase 3
- Tuesday, July 14: Phase 4
Streets Included
Phase 3
- Vail Lane
- Copper Court
- Portions of Alpine Drive
- Portions of Big Sky Drive
Phase 4
- Deer Valley Court
- Whistler Court
- Portion of Big Sky Drive
Important Information for Residents
On paving days, the contractor will begin applying the tack coat at 6 a.m. We ask that you have your vehicles parked in an area outside of the work zone prior to 6 a.m. on your paving day. We should have you back in your driveway by 7 p.m. that evening. The first step of the paving day process is to spray a tack coat on the road. We ask that you not drive, walk or allow your pets to walk on the tack coated areas – this sticky glue is not easy to remove from your car, shoes, driveways, or carpets and is not good for your pets’ paws.
Additional notes:
- Do not operate lawn sprinklers from July 13–15.
- If weather delays the project, paving will move to the following day.
- If your street is not completed on its scheduled paving day, crews will return the following morning to finish the work.
Please refer to the linked map to see the Phase 3 and Phase 4 work areas.
Thank you for your patience as these roadway improvements are completed.